Total of 10 Turbine foundations. Supply, Mix, Deliver and Install 6,000 m3 of concrete. Form, place and finish 10 towers.
Project Type:
Client:
AMECFMS / Black & McDonald Joint Venture
Date:
November 2017
Location:
Summerland BC
Value:
$2,560,000